Here is one week's work. Things are really progressing now. We have narrowed down the carpet selections, the sparky has started putting in the powerpoints and the cabinet handles should go on over the weekend. The walk in robe hasn't gone in yet but the materials have been ordered. The design I drew didn't fit in the room (never was a mathematician) so the cabinet maker had to re-design it all. Will be good to see how it works out.
Better pic of the ensuite
View of the kitchen from the stacker slider doors. they have been painting the doors so they are all spread out drying. We also had a couple of people come and measure up for the granite benchtops today.
View from the kitchen, up the main hallway to the open front door.